Focht3 and gandersen,
Thank-you for the input. Focht3, this project is in Madison, Wisconsin, it's glacial deposits (on a sideslope of a ridge so generally it's lacustrine soil overlying deeper glacial till). The soil profile is lean clay and silt in the upper 1/2 then clean sand with gravel below (about lower 10' to 15' would be below the water table, but very to extremely dense. Lowest level is about 40' below exterior grade. Knowing the site constraints, I would believe the backfill will qualify as "Chimney-like". It's below grade parking, so I'd also have to believe the system will be pretty rigid (poured concrete walls with precast plank decks). However, I'll know more within a couple weeks when I recieve a set of plans and specifications for my final review of how they match my recommendations.
I had thought about Peck's braced excavation pressure distribution, but I thought that required a "top-down" type construction process where the bracing is added as the excavation advances downward. Although I'm sure the selected contractor will use his preferred construction methods, I believe the design assumes standard construction (i.e., excavate to the design lowest foundation depth then construct the building using "bottom-up" construction). Am I wrong with this thinking?