pipe15
Mechanical
- Jul 22, 2005
- 69
Once the required wall thickness is calculated and a pipe schedule or thickness is selected based on Temp, Pressure, and allowances is there a criteria to check for collapse if the piping may be subject to a vacuum? I am guessing this may be an issue for lines above 30" with wall <=.5" or so, and especially large lines for circ water (>72").
Some of the lines are buried with appropriate trench and backfill requirements, but even there, should underground lines be checked too?
thanks
Mark
Some of the lines are buried with appropriate trench and backfill requirements, but even there, should underground lines be checked too?
thanks
Mark