martin888888
Civil/Environmental
- Jun 15, 2010
- 157
Quick question on the design and presentation for large piping. We have a 72" process pipe with a min slope of .25% needed for condensation and I&I drainage. When you have a 90 degree sweep in the pipe what is the "normal" way to design and present it on a set of plans. Do you design it and actaully show and profile through the sweep, or do you design and profile it through the PI as you do small diameter pipe? My feeling is that you do not show the sweep in the design. You will horizontally lay it out with the PI only and profile through the PI. The length through the sweep will be shown longer then it actualyl will be doing it this way however.
My experience with large pipe is limited so any imput is appreciated.
My experience with large pipe is limited so any imput is appreciated.