Shz713
Structural
- Aug 21, 2015
- 221
Hi everyone,
what is the best practice to represent parapet and kerb load of bridges as superimposed dead load? Should it be line load (N/M)?
If parapet is made up of steel and kerb made up of plain concrete, then we simply get cross section and multiply by density of material to get load per meter length. I have adapted such approach but I got 12.4 KN/m line load for parapet and kerb. Is this approach correct?
Besides, for deck wearing surface, I multiplied thickness of deck wearing to concrete density and applied it as pressure load (N/m^2) over entire deck surface. Is this correct practice?
Thanks Engineers![[bigsmile] [bigsmile] [bigsmile]](/data/assets/smilies/bigsmile.gif)
what is the best practice to represent parapet and kerb load of bridges as superimposed dead load? Should it be line load (N/M)?
If parapet is made up of steel and kerb made up of plain concrete, then we simply get cross section and multiply by density of material to get load per meter length. I have adapted such approach but I got 12.4 KN/m line load for parapet and kerb. Is this approach correct?
Besides, for deck wearing surface, I multiplied thickness of deck wearing to concrete density and applied it as pressure load (N/m^2) over entire deck surface. Is this correct practice?
Thanks Engineers
![[bigsmile] [bigsmile] [bigsmile]](/data/assets/smilies/bigsmile.gif)