parlitu
Electrical
- Mar 10, 2008
- 23
I start commissioning test for some switchgear 2 years ago. I did not finish commissioning, and due to company low budget, I had to stop this work for 2 years. Are those test that have been performed still valid? Or those test should be repeated again? Is any Standard that describe this? I will definitely repeat some, but will be just my judgement.