Hi,
In attached drawing, the key characteristic is the lower segment of the composite profile which controls perpendicularity and form of the cavity, and is the only one I want the metrology lab to inspect using CMM. The metrology lab is newly established and short of well trained and experienced inspectors. Look at the FRTZF of the composite profile tolerance callout, I would like to know:
Is the dimensioning and tolerancing scheme inspection friendly? The inspector I talked to does not think so. She kept saying she could not find a way to load the basic dimensions into PC-DMIS, not because she does not know how to use the software, but the way I draft the part.
What are the typical inspection steps to inspect the FRTZF?
Many thanks.
In attached drawing, the key characteristic is the lower segment of the composite profile which controls perpendicularity and form of the cavity, and is the only one I want the metrology lab to inspect using CMM. The metrology lab is newly established and short of well trained and experienced inspectors. Look at the FRTZF of the composite profile tolerance callout, I would like to know:
Is the dimensioning and tolerancing scheme inspection friendly? The inspector I talked to does not think so. She kept saying she could not find a way to load the basic dimensions into PC-DMIS, not because she does not know how to use the software, but the way I draft the part.
What are the typical inspection steps to inspect the FRTZF?