Can't verify the above equation, but tried an example and the results did not seem to be even be in the right ball park so I may have entered something wrong.
For 5 or 10 foot changes in structure height on spans that long, I don't think most would even consider the change in tension. If you are a PLS-CADD user with the SAPS feature, there is a routine in there to do just what you are considering.
If you are not on level ground, the tension may increase or decrease, depending on the pole being raised.