Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Importing from Excel

Status
Not open for further replies.

Sailinhorse

Chemical
Aug 7, 2003
1
Can one import a "% Work Complete" value generated in Excel into Project 2000? If not can you import the value into a Project "Number x" column?
 
Replies continue below

Recommended for you

Sailinhorse,

You can cut and paste Excel data into Project and vice versa. This is method recommended in the help

Funtime

 
Please excuse me if you already know how to perform this, but I find it a useful and very fast way of updating programmes.

Insert a column and define the field name as "% Work Complete" (if the column inserted is placed next to the ID or name it is easy to check the entry is at the corect position). The % complete information can then be entered, supermarket checkout style, using the numeric keyboard. The % complete column can then be hidden, if required.

The copy and paste command is fine too but very often it can cause problems if the paste is out by one row.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor