qqitek
Electrical
- Jun 15, 2010
- 13
Hello Folks!
I have question regarding IEC 60364-5-52 regarding approved methodes of cable routing via ladders/trays and derating factors.
Q1) Table B.52.17 item 1.
Can we use the worst reduction factor (0,38) for multilayer cable routing? It is very often that cables are laid on several layers laying each on other.
I would like to know how to derate cables in such situation?
Q2) If above is not accepted for multilayer laying of cables, look on IEC 60364-5-52 Table B.52.20 NOTE 2:
"NOTE 2 Factors apply to single layer groups of cables as shown above and do not apply when cables are installed in
more than one layer touching each other. Values for such installations may be significantly lower and has to be
determined by an appropriate method."
What is the "appropriate method" of calculating reduction factor in this case?
Any ideas?
thanks in advance,
qqitek
I have question regarding IEC 60364-5-52 regarding approved methodes of cable routing via ladders/trays and derating factors.
Q1) Table B.52.17 item 1.
Can we use the worst reduction factor (0,38) for multilayer cable routing? It is very often that cables are laid on several layers laying each on other.
I would like to know how to derate cables in such situation?
Q2) If above is not accepted for multilayer laying of cables, look on IEC 60364-5-52 Table B.52.20 NOTE 2:
"NOTE 2 Factors apply to single layer groups of cables as shown above and do not apply when cables are installed in
more than one layer touching each other. Values for such installations may be significantly lower and has to be
determined by an appropriate method."
What is the "appropriate method" of calculating reduction factor in this case?
Any ideas?
thanks in advance,
qqitek