We have 12 Nos 450T/h Doosan HRSGs installed at 2700 MW capacity CCGT.
After commissioning, EPC have not provided us any HMBD documents for HRSG.
We have found multiple erection defects in our HRSGs, and with the help of HMBD i want to prove that these erection defects (bypasses, insulation failures, etc) are impacting the performance.
I can ask for HMBD documents from EPC. I just want to know is there something else which should have been handed over to us as commissioning document for HRSG?
What is the standard set of handover documents that are supposed to be handed over to Operator by EPC on HRSGs?
Also is there any standard or code (ASME or other) which relates to HRSG construction defects?
Thanks for your feedback.
After commissioning, EPC have not provided us any HMBD documents for HRSG.
We have found multiple erection defects in our HRSGs, and with the help of HMBD i want to prove that these erection defects (bypasses, insulation failures, etc) are impacting the performance.
I can ask for HMBD documents from EPC. I just want to know is there something else which should have been handed over to us as commissioning document for HRSG?
What is the standard set of handover documents that are supposed to be handed over to Operator by EPC on HRSGs?
Also is there any standard or code (ASME or other) which relates to HRSG construction defects?
Thanks for your feedback.