rob5377
Chemical
- Oct 3, 2007
- 28
Hello
I need to hook up a new eqp to existing cooling water line. But the pressure in existing line is too small (assume 0.5 barg) I need at least 1 barg at device inlet. Is it possible to hook up a centrifugal pump to line? Then I could supply an equipment with water. Maybe I should use a diferent type of pump? Flow rate is ca 100 m3/hr.
Thanks for any suggestions.
I need to hook up a new eqp to existing cooling water line. But the pressure in existing line is too small (assume 0.5 barg) I need at least 1 barg at device inlet. Is it possible to hook up a centrifugal pump to line? Then I could supply an equipment with water. Maybe I should use a diferent type of pump? Flow rate is ca 100 m3/hr.
Thanks for any suggestions.