MarkHerring
Petroleum
- Mar 15, 2006
- 6
I have my main schedule and my target schedule....how do I update the target schedule?
what im trying to do is have my main target percent complete and compare it to where the job should actually be via the target schedule
for example..I update my main schedule for march 15th...and we are showing job as being 35% complete...i then update the target schedule and it is showing we should be at 40% complete.
updating the target correctly (i.e. not making a new target date) and having it show what the target percent is.
what im trying to do is have my main target percent complete and compare it to where the job should actually be via the target schedule
for example..I update my main schedule for march 15th...and we are showing job as being 35% complete...i then update the target schedule and it is showing we should be at 40% complete.
updating the target correctly (i.e. not making a new target date) and having it show what the target percent is.