Can someone help me with This problem ?. I designed a curved steel bridge with two U-trap twin steel sections . This is a single span bridge is 40m (~ 120ft ); deck width ~ 10.4m (~ 34ft ); Rad cl = 75.0m [ 246ft ] the construction will be shored composite . The contractor made the shop drawings and proceeded to fabricate the u-trap beams with straight segments ~ 5.0m [ 17ft ] length . I think to divide each segment in smaller of ~ 1.70m [ 6ft ~ ] ends skewed and joint them with butt welds . I need to know : is it a right solution?. If there any specification or limit to use in curved straight segments in this kind of bridges? What else must I to do in design verification or construction recomendations .