Hi,
We have just discovered a crack in the windage shroud in a 40MW 4000rpm coupling (turbine-gear) As always the OEM has quoted some 20 weeks delivery. In a previous job, circa 2003 I bought a 'copy' coupling from a firm in the USA on a much shorter turn time but it carried a hefty price tag. I have since moved jobs twice and lost the contact details.
Does anyone know who I might have dealt with? Does anyone know of an alternative supplier?
Thanks
Andrew
We have just discovered a crack in the windage shroud in a 40MW 4000rpm coupling (turbine-gear) As always the OEM has quoted some 20 weeks delivery. In a previous job, circa 2003 I bought a 'copy' coupling from a firm in the USA on a much shorter turn time but it carried a hefty price tag. I have since moved jobs twice and lost the contact details.