Hi, long time haven't post in here,
Right now i'm having a problem of making a decision whether a CSP pile is acceptable or not.
I had a report of a PIT (Pile Intergrity Test) of 13 driven CSP piles condition, the report contains the PIT Graphs and also the summary of BTA value.
From the BTA value summary, the lowest value is 85%, now i have found several journals about this BTA value which states that :
100 % (BTA Value) = Undamaged
80 ~ 99 % (BTA Value) = Slight damaged
60 ~ 79 % (BTA Value) = Damage
Below 60 % (BTA Value) = Broken
now if the BTA value is below 60% i would easily reject the piles, or even below 80% i could suggest a load test to determine whether the bearing capacity is acceptable or not.
But the slight damaged really confuses me, since there are 9 of the value are 95%, two are 85%, and one 100% (i attached the summary), it seems that this wouldn't be a problem so the piles are acceptable, but does anyone have a suggestion? can this BTA value can be used as a reference to accept the piles or not? since it only states the pile condition without determining what action should be done..
Thanks a lot before,
Sincerely
Jeff
Right now i'm having a problem of making a decision whether a CSP pile is acceptable or not.
I had a report of a PIT (Pile Intergrity Test) of 13 driven CSP piles condition, the report contains the PIT Graphs and also the summary of BTA value.
From the BTA value summary, the lowest value is 85%, now i have found several journals about this BTA value which states that :
100 % (BTA Value) = Undamaged
80 ~ 99 % (BTA Value) = Slight damaged
60 ~ 79 % (BTA Value) = Damage
Below 60 % (BTA Value) = Broken
now if the BTA value is below 60% i would easily reject the piles, or even below 80% i could suggest a load test to determine whether the bearing capacity is acceptable or not.
But the slight damaged really confuses me, since there are 9 of the value are 95%, two are 85%, and one 100% (i attached the summary), it seems that this wouldn't be a problem so the piles are acceptable, but does anyone have a suggestion? can this BTA value can be used as a reference to accept the piles or not? since it only states the pile condition without determining what action should be done..
Thanks a lot before,
Sincerely
Jeff