rideox4
Chemical
- Aug 8, 2008
- 3
I have a batch reactor where one of the intermediate steps is to pass the entire contents of the batch (reactor 1) over to reactor 2 for the mere purpose of passing the batch through a filter to remove solids on its way to reactor 2. Because we are processing it this way, 100% of the batch gets filtered. I want to change the process so that the filtration occurs via a recycle loop in reactor 1...instead of pumping it over to reactor 2 and then back to reactor 1. The problem with the recycle loop for filtration is that we can never be sure that 100% of the batch will actually make it through the recycle loop due to residence time distribution issues.
question: Is there a rule-of-thumb for the recycle time required or # of batch turnovers required to assume that 100% (or 99%+) of the product makes it through the recycle loop? I assume it is related to a rule-of-thumb of Residence Time Distributions for a batch reactor and may be related to the recylce rate, mixing rate, etc. Let's assume perfect mixing.
Help!!
Thank You
question: Is there a rule-of-thumb for the recycle time required or # of batch turnovers required to assume that 100% (or 99%+) of the product makes it through the recycle loop? I assume it is related to a rule-of-thumb of Residence Time Distributions for a batch reactor and may be related to the recylce rate, mixing rate, etc. Let's assume perfect mixing.
Help!!
Thank You