Nuccio
Geotechnical
- Sep 18, 2008
- 20
I have a job that I am doing the concrete work and excavation and underpinning. In one corner there will be a 17' deep cut along an existing building and front sidewalk. The building will be jacked up and supported on steel so we can excavate and build new foundations. But the front corner along the sidewalk will need to be shored. The site engineers want no vibration because of the existing structure are 100+ years old rubble foundation not in good shape. The boring for that location shows fill for the first 4-5 feet N Value 12- 17, then brown clayey silt with trace of fine sand from 5-10 feet N Value 11-10, then Grey clayey silt with trace of fine sand from 10-30 feet with N Values 10-12. Ground water was at 22 feet. I have evolved an engineer to come up with some designs. I was think if it is possible to use a 1 3/4" helical pile with a 10"12"14" helices as the lead and then add an displacement plate to install a 6" Sch. 40 steel casing to be grouted solid. So I would like to install these piles as solider piles 6' OC with wood lagging total dept.35 feet so you will have a 17'6" embedment and 17'6" pile sticking up out of the cut. What I am trying to eliminate is using tiebacks or al east use a little as possible so we avoid the utilities in the street.