raptorboy
Civil/Environmental
- Feb 13, 2006
- 3
Hi,
I'm a new user of HEC-HMS and I have been trying to model a basin using an SCS Type II distribution curve. The problem is, the agency requires that I use a 6-hour distribution curve for teh SCS hydrograph instead of the 24-hour distribution curve that is built into the program. I can't seem to find a way to set up my model for a 6-hour SCS Type distribution curve. Is this possible using HEC-HMS or am I out of luck?
I'm a new user of HEC-HMS and I have been trying to model a basin using an SCS Type II distribution curve. The problem is, the agency requires that I use a 6-hour distribution curve for teh SCS hydrograph instead of the 24-hour distribution curve that is built into the program. I can't seem to find a way to set up my model for a 6-hour SCS Type distribution curve. Is this possible using HEC-HMS or am I out of luck?