DCMV
Petroleum
- Nov 5, 2011
- 35
We are building a new pressure vessel per ASME Sect VIII Div 1. We have completed the vessel and pressure tested the vessel with AI present and stamped. Now we noticed the Client drawings call for the internal welds ground flush. Do we have to re-hydro the vessel if we just grind the welds smooth and flush?