macmet
Materials
- Jul 18, 2005
- 863
We have a customer who is looking to flush their system before any of the external piping is complete as part of their pre-commissioning. We consider our flushes to be high flow, low pressure relatively speaking(150usgpm, 100psi for example).
We are rarely on-site during the flush, and even when we are, the work is generally complete to the point where the inlet has the flanges welded to it. But, as none of their external piping is complete, they have yet to weld any flanges on to the outside of their unit. All we have to connect to are 3", 4", 8" and 10" schedule 120 stainless pipes which extend 4-6" beyond the boundary of their unit. I was told there are connectors that can be used to connect a flush hose to these size pipes, but I haven't been able to track it down on google. I'm working with a language barrier as well and if anyone could tell me the proper term for these connectors I would really appreciate it.
I feel like this is something that is quite common, but I'm struggling finding the proper item.
Customer is not likely to run water through their unit for a number of months, but they need to flush in the next few weeks to allow their commissioning schedule to proceed.
Cheers
We are rarely on-site during the flush, and even when we are, the work is generally complete to the point where the inlet has the flanges welded to it. But, as none of their external piping is complete, they have yet to weld any flanges on to the outside of their unit. All we have to connect to are 3", 4", 8" and 10" schedule 120 stainless pipes which extend 4-6" beyond the boundary of their unit. I was told there are connectors that can be used to connect a flush hose to these size pipes, but I haven't been able to track it down on google. I'm working with a language barrier as well and if anyone could tell me the proper term for these connectors I would really appreciate it.
I feel like this is something that is quite common, but I'm struggling finding the proper item.
Customer is not likely to run water through their unit for a number of months, but they need to flush in the next few weeks to allow their commissioning schedule to proceed.
Cheers