httc78
Civil/Environmental
- May 5, 2006
- 2
I am involved with a project to construct vehicular viaduct. the contractor was not able to finish the foundation works and there are currently a few caissons that has been fully excavated and flooded with water. a combination of high water table and rain.
as the caisson has been completed for some time, it has been left flooded and i am concerned about its overall capacity after being exposed to such prolonged period of exposure to water.
is there a genuine concern for thinking that there is a tendency that the capacity has reduced substantially? if so, is there a way of ascertaining the capacity of the soil around the completed caissons?
the caissons varies between 3 to 6m in diameter and toe levels at 50-60m beneath ground level. soil around the site are generally sand and sandy clay. beneath 30m, the ground consist of stiff clay which is used for socketing as the top half is debonded for future works.
as the caisson has been completed for some time, it has been left flooded and i am concerned about its overall capacity after being exposed to such prolonged period of exposure to water.
is there a genuine concern for thinking that there is a tendency that the capacity has reduced substantially? if so, is there a way of ascertaining the capacity of the soil around the completed caissons?
the caissons varies between 3 to 6m in diameter and toe levels at 50-60m beneath ground level. soil around the site are generally sand and sandy clay. beneath 30m, the ground consist of stiff clay which is used for socketing as the top half is debonded for future works.