PEVT
Civil/Environmental
- Mar 28, 2008
- 18
I am designing the tension reinforcement within the stem of a cantilever retaining wall. This wall, like most walls, is tall enough that it would be very inconvenient to require that the bars be placed full height at the time of the footing pour. I would like to provide a lap splice of the tension reinforcement within a reasonable distance of the top of the footing and so I think I must meet the provisions of ACI 12.10.5. Is this correct? Most designs I have seen for this scenario provide for the wall's moment and shear requirements, specify the general tension development length but do not address the fact that there is a termination in the tension zone.