Hello
I have been asked to price as part of package approx 1000metres of galvanized balustrade to a 12 floor block of appartments,the client needs the fixing of the standards on the underside of the concrete balcomies, producing a cantelever.
My issues are, the welfare of my labour drillig 1000,s of 16mm holes upside down,supporting 250kg sections of the balustrade prior to fixing and the line and levelof the balustrade being reliant on the accuracy of the concrete.
I would appreciate any imput
regards
welder 88
I have been asked to price as part of package approx 1000metres of galvanized balustrade to a 12 floor block of appartments,the client needs the fixing of the standards on the underside of the concrete balcomies, producing a cantelever.
My issues are, the welfare of my labour drillig 1000,s of 16mm holes upside down,supporting 250kg sections of the balustrade prior to fixing and the line and levelof the balustrade being reliant on the accuracy of the concrete.
I would appreciate any imput
regards
welder 88