A power cable is going to be put through my land alongside an open drainage ditch.
My main concern with this is ensuring the field drainage is done properly as maintenance after the fact will be difficult.
The contractor is intending to put the drainage under the cable as per below. Is this typical? Or would the cable ever be put so deep that the drainage can go over the top?

My main concern with this is ensuring the field drainage is done properly as maintenance after the fact will be difficult.
The contractor is intending to put the drainage under the cable as per below. Is this typical? Or would the cable ever be put so deep that the drainage can go over the top?