Zambo
Civil/Environmental
- Jun 5, 2003
- 697
We are to construct a falsework to support a segmental bridge structure prior to post-tensioning. The segments will total about 500 tonne and then there is the load from a 20m high falsework. The plan area of the falsework will be around 200m2, but we are still considering using a tower system rather than spreading the load over the full area.
We have some earlier broehole results from the feasibility study which shows that the soil is a sandy clay with N values around 5. We will now proceed to carry out further testing to decide on the construction method. We are planning some soil improvement, probably just by replacing the upper layers with a better material and then we will precast concrete slabs and prestress them together (several spans to do these slabs will be reused)
My question is, as we are considering short term loading (around 20 days with the full load) are plate bearing tests useful? Apart from SPT tests, are there any other suggestions?
Should mention that where I am working we must specify the testing and just tell the geothechnical company what to do - sound advice not available.
Zambo
We have some earlier broehole results from the feasibility study which shows that the soil is a sandy clay with N values around 5. We will now proceed to carry out further testing to decide on the construction method. We are planning some soil improvement, probably just by replacing the upper layers with a better material and then we will precast concrete slabs and prestress them together (several spans to do these slabs will be reused)
My question is, as we are considering short term loading (around 20 days with the full load) are plate bearing tests useful? Apart from SPT tests, are there any other suggestions?
Should mention that where I am working we must specify the testing and just tell the geothechnical company what to do - sound advice not available.
Zambo