Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

ETABS shear wall-column design

Status
Not open for further replies.

MattBob

Structural
Nov 30, 2013
1
Hi,
Does anybody know how come the results for design of a concrete shear wall with two columns at the ends of the wall is different from area of rebars for the columns in "Concrete design/check of structure"? I designed a shear wall with columns and modeled the wall with wall section and columns and for designing shear wall I used "General method" with "pier Section". Design of column itself shows I need 6% area of reinforcement and design of shear wall with "pier section" that includes shear wall and columns needs 2% area of reinforcement in columns. Thanks for your help.

Matt
 
Replies continue below

Recommended for you

That issues are common in ETABS. In order to design walls, I use that tool. The wall forces are extracted from ETABS using Display->Show Tables->Copy Entire Table (to Excel) and then the design process continues on this external program, which I higly recommend.

Regards,

Gigi
 
as stated by Johnbridge,

you need to :

1) Extract pier forces from Etabs
2) Design by sectional analysis (Can be done easily by excel spreedsheet or any column sectionnal analysis software like spColums, etc...)
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor