auzie5
Mechanical
- May 8, 2009
- 94
I’m curious if anyone here has ever completed an Engineering Assessment (EA) to support a non-conformance to a code requirement during new construction. This is primarily a philosophical question since CSA Z662-15 is unclear regarding whether or not an EA can be adopted at the construction stage.
It usually never comes up since we typically just remove any defects that are discovered at the construction stage. However there are some extreme cases where it may not be practical to remove a defect that can be shown to pose no integrity concerns for the pipeline system.
Example:
After pipeline construction but prior to commissioning, an ILI caliper tool run identifies ovality in a section of the pipeline. The ovality is measured to be 6%. Estimated cost to remove and replace the section of pipe with ovality is one million dollars. An engineering assessment of the ovality demonstrates that the ovality does not jeopardize the integrity of the pipeline system.
However, the pipeline is built to CSA Z662-15. CSA Z662-15 Clause 6.3.4.2 states, “Pipe out of roundness shall be limited to the difference between the maximum and minimum diameters not exceeding 5% of the specified outside diameter of the pipe. Pipe not meeting this requirement shall be removed”.
Nowhere in CSA Z662-15 Clause 6 does it state that an EA can be used to support a non-conformance to a code requirement during new construction.
Any thoughts? Has anyone here ever completed an EA to accept a non-conformance to a code requirement during new construction using any other codes? Possibly on an offshore pipeline project where repair costs tend to be relatively high compared to onshore repair work?
I appreciate any insight provided on this matter.
Thanks.
It usually never comes up since we typically just remove any defects that are discovered at the construction stage. However there are some extreme cases where it may not be practical to remove a defect that can be shown to pose no integrity concerns for the pipeline system.
Example:
After pipeline construction but prior to commissioning, an ILI caliper tool run identifies ovality in a section of the pipeline. The ovality is measured to be 6%. Estimated cost to remove and replace the section of pipe with ovality is one million dollars. An engineering assessment of the ovality demonstrates that the ovality does not jeopardize the integrity of the pipeline system.
However, the pipeline is built to CSA Z662-15. CSA Z662-15 Clause 6.3.4.2 states, “Pipe out of roundness shall be limited to the difference between the maximum and minimum diameters not exceeding 5% of the specified outside diameter of the pipe. Pipe not meeting this requirement shall be removed”.
Nowhere in CSA Z662-15 Clause 6 does it state that an EA can be used to support a non-conformance to a code requirement during new construction.
Any thoughts? Has anyone here ever completed an EA to accept a non-conformance to a code requirement during new construction using any other codes? Possibly on an offshore pipeline project where repair costs tend to be relatively high compared to onshore repair work?
I appreciate any insight provided on this matter.
Thanks.