Dec 12, 2013 #1 TLCPA Electrical Joined Jan 23, 2009 Messages 13 Location US Pennsylvania is getting a lot of drilling pads for Marcellus shale. These drilling pads can have 3 MW or more of diesel generators supplying motors as large as 1600 HP. What is the appropriate electrical code for these drilling pads?
Pennsylvania is getting a lot of drilling pads for Marcellus shale. These drilling pads can have 3 MW or more of diesel generators supplying motors as large as 1600 HP. What is the appropriate electrical code for these drilling pads?
Dec 13, 2013 Moderator #2 waross Electrical Joined Jan 7, 2006 Messages 28,695 Location CA Basic NEC plus API (American Petroleum Institute). API grounding of equipment is much more stringent than NEC requirements. Bill -------------------- "Why not the best?" Jimmy Carter Upvote 0 Downvote
Basic NEC plus API (American Petroleum Institute). API grounding of equipment is much more stringent than NEC requirements. Bill -------------------- "Why not the best?" Jimmy Carter