lovethecold
Civil/Environmental
- Sep 15, 2003
- 97
I am preparing a report for a guyed tower approximately 500 feet tall. The tower has a downward load of 165kips and a lateral load at the base of 2 kips. I spoke with the engineer and contractor and they prefer to use a mat foundation at frost depth (~7'). We would prefer this as well. However, I am looking to give recommendations for support of the tower using a drilled pier. The problem with this at the site in question is a dense water bearing sand layer about 30 feet below the surface.
During drilling, when our driller first encountered this layer, the sand heaved several feet up into the auger and water rose to approximately 2 feet below the surface almost immediately. The soil above consists of sandy lean clay with average bpf of 8 down to 17 with an average bpf of 20 below this. There is a water bearing sand layer about 4-6 feet (this doesn't appear to be under pressure and didn't cause problems during drilling). The are around the tower location is a slough. The tower is only about 4 feet above the slough and many of the guy anchors will be in the slough.
My question becomes is it even feasible to consider a drilled pier at this location? If so, is it possible to calculate what sort of pressure the dense waterbearing sand is under to know how far above this layer the drilled pier should stop to avoid the sand blowing up into the drilled shaft and creating some most undesirable problems?
I should also say that when drilling at one of the guy anchor locations, the sand blew up into the auger causing the center bit to become stuck in the auger. To remove, the crew had to pull the auger and drill rod together in order to recover them. The sand at the guy anchors begins between 26 and 27 feet.
Thanks for any advice.
During drilling, when our driller first encountered this layer, the sand heaved several feet up into the auger and water rose to approximately 2 feet below the surface almost immediately. The soil above consists of sandy lean clay with average bpf of 8 down to 17 with an average bpf of 20 below this. There is a water bearing sand layer about 4-6 feet (this doesn't appear to be under pressure and didn't cause problems during drilling). The are around the tower location is a slough. The tower is only about 4 feet above the slough and many of the guy anchors will be in the slough.
My question becomes is it even feasible to consider a drilled pier at this location? If so, is it possible to calculate what sort of pressure the dense waterbearing sand is under to know how far above this layer the drilled pier should stop to avoid the sand blowing up into the drilled shaft and creating some most undesirable problems?
I should also say that when drilling at one of the guy anchor locations, the sand blew up into the auger causing the center bit to become stuck in the auger. To remove, the crew had to pull the auger and drill rod together in order to recover them. The sand at the guy anchors begins between 26 and 27 feet.
Thanks for any advice.