TTUengr51
Structural
- Jul 19, 2005
- 63
I am currently working on a large warehouse structure utilizing tilt-up construction for the perimeter walls. I have an open web steel joist roof structure covered with metal decking. Due to the size of the structure and a step in the roof plane, I have 3 individual diaphragms to design.
I am in Seismic Design Category C (2006 IBC) and seismic is definitely controlling due to the weight of the tilt-up panels (45' to top of parapet).
The question I have concerns the out of plane forces generated by the tilt-up walls. In transferring the forces into the diaphragm, I am creating smaller sub-diaphragms to collect the load to my continuous struts/ties. My continuous strut/tie will be either an open web joist or joist girder at my column lines.
My questions are as follows:
1) Do the strut/tie forces need to be carried across the entire length of the building, making sure each connection to the column and next strut/tie in line can carry this force? Or do I account for them until I have an adequate diaphragm length to dissipate the force, similar to how a collector element between shear walls or braced frames?
2) How should I contend with the strut/tie force in the design of the open web joist/girder? Is this as simple as noting an axial load on the plan for the open web joist/girder designer to content with? This seems right, but I have never seen such forces noted on other structural drawings before. The sub-diaphragms will require a joist/girder to be a chord element. I would imagine this force should be shown on the plan as well.
Any help and/or thoughts would be greatly appreciated.
I am in Seismic Design Category C (2006 IBC) and seismic is definitely controlling due to the weight of the tilt-up panels (45' to top of parapet).
The question I have concerns the out of plane forces generated by the tilt-up walls. In transferring the forces into the diaphragm, I am creating smaller sub-diaphragms to collect the load to my continuous struts/ties. My continuous strut/tie will be either an open web joist or joist girder at my column lines.
My questions are as follows:
1) Do the strut/tie forces need to be carried across the entire length of the building, making sure each connection to the column and next strut/tie in line can carry this force? Or do I account for them until I have an adequate diaphragm length to dissipate the force, similar to how a collector element between shear walls or braced frames?
2) How should I contend with the strut/tie force in the design of the open web joist/girder? Is this as simple as noting an axial load on the plan for the open web joist/girder designer to content with? This seems right, but I have never seen such forces noted on other structural drawings before. The sub-diaphragms will require a joist/girder to be a chord element. I would imagine this force should be shown on the plan as well.
Any help and/or thoughts would be greatly appreciated.