DRLEI
Structural
- Apr 3, 2010
- 2
Have a topic regarding a Cantilever "L " Retaining Wall that is supported on a footing that is to be supported on Helical Pull Down Piles. Pile spacing in the front row (under the stem wall) is approx. 5 feet and about double that in the back row (at the heel). Height of retention is less than 5 feet and it serves at the end of driveways (mulitiple walls involved) into underbuilding garages on a man made island (earth fill and organice below hence the need for piles (buildings are on piles). Anyone have knowledge of a program (or other) that will design the footing for thickness to act sufficiently rigid to distribute loads to the piles and size the reinforcing for both the negative and positive bending zones between the piles. The footings (walls) are approximately 28 and 36 feet long (separate conditions based on site features and requirements).