Jun 15, 2018 #1 Metma Mechanical Joined Feb 21, 2008 Messages 21 Location IT Referring to para 304.3.3 of B31.3, is the calculation formula applicable to 'Set In' configuration (branch insterted in the cutted Run Pipe) or to 'Set On' configuration (branch put on the cutted Run Pipe)? thx https://files.engineering.com/getfile.aspx?folder=f03faa28-aad2-4d09-87b0-bfce5d2a2d1d&file=Set_in_-_Set_on.pdf
Referring to para 304.3.3 of B31.3, is the calculation formula applicable to 'Set In' configuration (branch insterted in the cutted Run Pipe) or to 'Set On' configuration (branch put on the cutted Run Pipe)? thx
Jun 15, 2018 #2 LittleInch Petroleum Joined Mar 27, 2013 Messages 23,036 Location GB It can be either, but the default appears to be set on. The definition of d1 varies depending on whether the pipe is set on or set in "...projection of the branch pipe inside diameter..." Remember - More details = better answers Also: If you get a response it's polite to respond to it. Upvote 0 Downvote
It can be either, but the default appears to be set on. The definition of d1 varies depending on whether the pipe is set on or set in "...projection of the branch pipe inside diameter..." Remember - More details = better answers Also: If you get a response it's polite to respond to it.