monopoly
Structural
- Oct 29, 2006
- 28
Hi all,
We design foundations of the oil tanks (diameters vary from 30-55m, height 12-13m) with concrete ring walls (the ring wall is required for uplift resisstance). Inside the ring wall the bottom of the tank is rested on the 80mm minus run gravel compacted to 100% SPMDD, with thickness of 1m. under the gravel layer is the engneered fill of about 1.5m thick, then the stiff to very stiff native clay. And we intended to install the high temperature geotextile for secondary liner under the tank.
The problem now is the temperature of the oil inside the tank is up to 90 degree celsius. Geotechnical engineer for the project said that the 2.5m of gravel and engineered fill above the clay is enough for the dissipated of the temperature when it transered to clay. but still warry about the desiccation settlelemnt of clay down bellow.
Any document or reference to check that problem. or any experience with that kind of design?
We design foundations of the oil tanks (diameters vary from 30-55m, height 12-13m) with concrete ring walls (the ring wall is required for uplift resisstance). Inside the ring wall the bottom of the tank is rested on the 80mm minus run gravel compacted to 100% SPMDD, with thickness of 1m. under the gravel layer is the engneered fill of about 1.5m thick, then the stiff to very stiff native clay. And we intended to install the high temperature geotextile for secondary liner under the tank.
The problem now is the temperature of the oil inside the tank is up to 90 degree celsius. Geotechnical engineer for the project said that the 2.5m of gravel and engineered fill above the clay is enough for the dissipated of the temperature when it transered to clay. but still warry about the desiccation settlelemnt of clay down bellow.
Any document or reference to check that problem. or any experience with that kind of design?