psychedomination
Structural
Hi there,
I am a graduate engineer and am currently looking into designing footings for two columns. The loads on the columns are very small at 150kN and 60kN respectively.
Due to the small loads I only needed to use the minimum bending reinforcement for both hogging and sagging moments.
The column taking the 150kN load will be cast against a wall that is to be excavated. The 60kN column is to be cast against the property line. Due to this I designed a combined footing between the 60kN column and the 150kN column.
As such, I needed the 150kN column to have a proper pad footing with no eccentricity.
Before the wall and area behind it is excavated I wanted to put up the columns and beams in place to hold up the floor slab in the event that anything unexpected happened.
I am thinking to pour 2/3 of the footing first on the un-excavated side as shown in the attached drawing. Then excavate the wall and about 3 feet behind it, putting up the required shoring jacks as needed and then pour the other 1/3 of the footing. I am thinking to connect the other 1/3 of the footing with post installed rebars epoxied in and then wetting and roughening the surface vertically before pouring the second 1/3 pour.
What are your thoughts on this seeing as all of the loads are so low? The concrete for the first 2/3 pour would be compacted fine as it will be cast against compacted earth, same with the last 1/3 pour.
I was getting a low bearing pressure of 53kPa in the combined footing.
Any advice would be appreciated.
I am a graduate engineer and am currently looking into designing footings for two columns. The loads on the columns are very small at 150kN and 60kN respectively.
Due to the small loads I only needed to use the minimum bending reinforcement for both hogging and sagging moments.
The column taking the 150kN load will be cast against a wall that is to be excavated. The 60kN column is to be cast against the property line. Due to this I designed a combined footing between the 60kN column and the 150kN column.
As such, I needed the 150kN column to have a proper pad footing with no eccentricity.
Before the wall and area behind it is excavated I wanted to put up the columns and beams in place to hold up the floor slab in the event that anything unexpected happened.
I am thinking to pour 2/3 of the footing first on the un-excavated side as shown in the attached drawing. Then excavate the wall and about 3 feet behind it, putting up the required shoring jacks as needed and then pour the other 1/3 of the footing. I am thinking to connect the other 1/3 of the footing with post installed rebars epoxied in and then wetting and roughening the surface vertically before pouring the second 1/3 pour.
What are your thoughts on this seeing as all of the loads are so low? The concrete for the first 2/3 pour would be compacted fine as it will be cast against compacted earth, same with the last 1/3 pour.
I was getting a low bearing pressure of 53kPa in the combined footing.
Any advice would be appreciated.