Some other things to consider are
Tolerances
Is the installation tolerance specified and realistic? If not realistic can it be relaxed or will some other technique be necessary to achieve the required tolerance?
Weather
Can the thing be built considering the weather to be expected at the time of the construction? Here in Canada sometimes special measures have to be incorporated into the specifications to allow for construction in the winter.
Interference of other trades? Mechanical systems interfering with structural is obvious one, electrical requirements matching the equipment loads is another one.
Code checks
Exits to code?
How about hazardous electrical areas being clearly identified? I once had a set of drawings that showed an electrical hazardous area on the electrical but specified non rated door operators. This needed a change order and additional money from the owner and caused a delay in occupancy of the project.
Repeated information the same every place it is repeated? Information should only be repeated as few times as possible to avoid getting any information incorrect, however if repeating information is necessary it should be consistent.
Is all the information in the correct place in the tender package? For example the geotechnical report should not go in the contract but is separate section called information for bidders. That way you are presenting the information and allowing the bidder to make up their own minds on the impact of the report and not being contractually bound for the report to be correct and 100% accurate.
Also anything that applies to the bidding process should be in the information for bidders and not in the contract. If it’s in the contract then you are saying that here is the contract and it will not have effect until it’s signed but you are expecting that something before the contract has effect to be done and be binding.
Are the materials specified available locally? When I worked for the federal government it was common for material only available in one part of the country to be specified for jobs in another part of the country.
Is there a simpler way to do the task? I once worked on a project that had a number of tanks and liquid was to flow by gravity between the different tanks. The design called for all the tanks to be constructed on concrete stands at many different levels. We changed the design to steel stands and were able to save a lot of money and time on the project.
Mostly it is an experienced based task. You can learn design from a book and by doing it, you can only learn constructability reviewing by having actually built many projects. It also should not be a final check of the package just before tender call but an ongoing part of the design process. That way the concrete stands would never have been designed in the first place
Rick Kitson MBA P.Eng
Construction Project Management
From conception to completion