Removing the flat plate slab of three lower floors in an existing 24 story building due to sever corrosion of the top and bottom reinforcing steel. Removal will reach 50% of each floor area.
Any information for reinforcing steel detail to re-establish slab and column connection (intending to keep the slab concrete within the column)