aladdin76
Civil/Environmental
- Dec 10, 2005
- 25
I am designing foundations and concrete ground beam for a pre-fabricated steel structure ( single story 40m x120m), the beam is 0.6m high and should support a hollow block cement wall, 3m high , the upper 0.2m of the beam is above ground level
my question is about the expansion joint , the spacing isn’t the issue , the issue is the detailing of the expansion joint, is splitting the ground beam with shared foundation is enough or it requires splitting both the beam and foundation.
my question is about the expansion joint , the spacing isn’t the issue , the issue is the detailing of the expansion joint, is splitting the ground beam with shared foundation is enough or it requires splitting both the beam and foundation.