Mar 28, 2012 #1 r0b3rt0p Chemical Joined Sep 13, 2011 Messages 6 Location IT Hi anyone can help me? In your company (engineering), which section have to wright new piping class specifications? it's process? tx bye
Hi anyone can help me? In your company (engineering), which section have to wright new piping class specifications? it's process? tx bye
Mar 28, 2012 #2 SeanB Chemical Joined Jun 11, 2003 Messages 258 Location CA Usually performed by the Materials engineer - not process. Upvote 0 Downvote
Mar 28, 2012 #3 TD2K Chemical Joined Jan 11, 2002 Messages 2,629 Location US Mechanical here. Process provides some input but Mechanical is the group that puts the piping spec together. Upvote 0 Downvote
Mechanical here. Process provides some input but Mechanical is the group that puts the piping spec together.
Mar 30, 2012 #4 moltenmetal Chemical Joined Jun 5, 2003 Messages 5,504 Location CA Both chemical and mechanical engineers prepare pipe specs here, but a mechie always looks it over before it goes into circulation. Upvote 0 Downvote
Both chemical and mechanical engineers prepare pipe specs here, but a mechie always looks it over before it goes into circulation.