we are commissioning a plant processing cane molasses to bakers yeast in Kenya. i have a problem with commissioning of the clarifier used to clarify mollasses fron solids before sterilisation. the separator/ clarifier is of type BRPX 213SGT/P/T-30T/CT it has a problem of no material comes out of outlet afert we confirmed the assemmbly is ok. the height adjustment of the paring disc has been done and all the selonoid valves have been programmed as per the manual. i have tried for a week but it seems their no impprovement. the seal ring 74722 are all replaced and everthing seems ok , idont know what is wrong before i call the expensive alfalaval rep. thanks .

D. Kipkosgei
Chemical engineer.

Dickens K. Seroney (B. Tech in Chem and process eng.)Moi,Kenya
Planning and development engineer.
 