davidfi
Structural
- Sep 28, 2005
- 39
I have a project under construction in which the batch plant closed and they ran out of concrete while pouring a large footing. I have a 18"x24" conc column that sits on what was supposed to be a 12' sq x 2'-6" thick footing. The footing as poured is only 2'-0" thick. I checked the 2'-0" thick footing; bending and one-way shear are fine, but the D/C for punching shear is 1.30.
My thought would be to drill and epoxy dowels at 8" oc each way and pour the remaining 6" of concrete.
How would you handle this?
Thanks!
My thought would be to drill and epoxy dowels at 8" oc each way and pour the remaining 6" of concrete.
How would you handle this?
Thanks!