jeffhed
Structural
- Mar 23, 2007
- 286
I have a PEMB steel building that the contractor did not order a special inspection. The building is 100% complete and the lack of special inspection only came up after the contractor went to the city to get their CO. We have since found out that the installed anchor bolts were only embedded half as deep as the plans required. I need to increase the size of the existing base plate to accomodate the new bolts we will be epoxying into the footing. The added portions of base plate will be the same depth as the original base plate and will run parallel with the column web. I originally thought to support the new sections of base plate with gusset plates perpendicular to the column web. A second option would be to overlay the existing base plate with plate that is the thickness I need and weld it to the column flanges and web (I could even remove the existing nuts and bolt this new plate to the existing plate in addition to the welding). Have others done similar retrofits? If so, is there some input you could provide as to why or why not one of these solutions would be acceptable? Obviously better ideas are definitley welcome.