ChemEngSquirrel
Chemical
- Jun 10, 2010
- 72
I have a piping system containing well production fluids (hydrocarbon gas, oil, water).
Would it be acceptable to depressurise this line to a knockout drum and vent when required for maintenance?
The vent is open to air and is not purged. There is no liquid seals to minimise air ingress. Therefore, all vent lines and the KO drum will be air filled until depressurisation of the hydrocarbon inventory takes place.
Would it be acceptable to depressurise this line to a knockout drum and vent when required for maintenance?
The vent is open to air and is not purged. There is no liquid seals to minimise air ingress. Therefore, all vent lines and the KO drum will be air filled until depressurisation of the hydrocarbon inventory takes place.