haynewp
Structural
- Dec 13, 2000
- 2,327
I talked to someone at SMI rebar who said that walls 24' high or so are being specified with continuous rebar more often (no splices allowed).
I am somewhat perplexed as to how this will work. Where I am, usually low lift grouting and 48 bar diameter splices for the wall reinforcing is what I have seen used.
I know that nobody is going to thread the blocks over the top of the reinforcing as the wall is built. Therefore, the only option I see is to pour from 24', which would seem to cause a lot of voids in the grout as you go down the wall.
1)Is this actually being done? And if so, wouldn't
cleanouts be required going up the wall
vertically?
2)How can the bottom lifts be effectively consolidated from
20' above?
3)How could you possibly tell what the final position of
the rebar would be in the wall towards the bottom of the
pour?
I am somewhat perplexed as to how this will work. Where I am, usually low lift grouting and 48 bar diameter splices for the wall reinforcing is what I have seen used.
I know that nobody is going to thread the blocks over the top of the reinforcing as the wall is built. Therefore, the only option I see is to pour from 24', which would seem to cause a lot of voids in the grout as you go down the wall.
1)Is this actually being done? And if so, wouldn't
cleanouts be required going up the wall
vertically?
2)How can the bottom lifts be effectively consolidated from
20' above?
3)How could you possibly tell what the final position of
the rebar would be in the wall towards the bottom of the
pour?