ajk1
Structural
- Apr 22, 2011
- 1,791
I am interested in views on "closure strips" in suspended slabs. These are about 1 m wide strips left out of the suspended slab placements, for at least 28 days after the concrete is placed in tne floor each side of the closure strip, to allow some of the shrinkage to occur before the concrete is placed in the closure strip.
We figure that about 30% of the long term shrinkage will have occurred at 28 days after completion of the 7 day curing perod (i.e 35 days after placing the slab).
However contractos don't like the 28 day period and want to reduce it to 7 days, but at 7 days after the 7 day cure we figure that only perhaps 10% of the long term shrinkage will have occurred, which would not accomplish our goal of minimizing shrinkage cracking, This is particularly important where the slab soffit forms the finished ceiling of the apartments.
I am interested in knowing if closure strips as described above are generally being used?
If so, for how long do you keep them open?
Any other way that you are dealing with shrinkage, or do you just ignore it?
We figure that about 30% of the long term shrinkage will have occurred at 28 days after completion of the 7 day curing perod (i.e 35 days after placing the slab).
However contractos don't like the 28 day period and want to reduce it to 7 days, but at 7 days after the 7 day cure we figure that only perhaps 10% of the long term shrinkage will have occurred, which would not accomplish our goal of minimizing shrinkage cracking, This is particularly important where the slab soffit forms the finished ceiling of the apartments.
I am interested in knowing if closure strips as described above are generally being used?
If so, for how long do you keep them open?
Any other way that you are dealing with shrinkage, or do you just ignore it?