EMWWW
Civil/Environmental
- Aug 26, 2020
- 8
We are working on retrofitting a Clarifier with new Internal Mechanisms. The Project is located in California. The Clarifier itself was built to an earlier Code and Seismic requirements (2016). What are the compliance requirements for such a retrofit, and how can the design reconcile the different loading guidelines per the two Codes?