rn14
Structural
- Aug 30, 2006
- 79
We recieved an RFI stating that due to material availability a shop splice will be required for a W33x201 we speced. The fabricator said the splice is to be a complete-joint-penetration weld and weld access holes filled, all to be tested with ultrasonic testing.
My manager wants to aswer the RFI by saying that we require one critical splice calculation.
Is there even a calculation to be performed? When I was in school we were always told there was nothing to be checked on a CJP weld.
My manager wants to aswer the RFI by saying that we require one critical splice calculation.
Is there even a calculation to be performed? When I was in school we were always told there was nothing to be checked on a CJP weld.