Rpsfinest
Electrical
- Dec 8, 2006
- 29
At my current plant we treat our cooling tower basins with chlorine dioxide. During the shoulder months when the plant isn't being dispathced we still feed the clorine dioxide once a day untill we reach a level of 600 ORP. Unfortunetly when the plant is down and we have no need for make-up water, the HCL in the chlorine dioxide drives the tower pH down below our operating range. This causes us to dump a bag of soda ash into the basins to bring the pH back up. To get away from dumping the soda ash in the basin I was thinking of setting up the chlorine dioxide units to just feed Bleach. Will I get the same oxidizing potential as I do with the Chlorine dioxide? What risk do I run by continuing to treat the basins with a bag of soda ash? we are currently using about a bag per week per basin...
thanks folks
thanks folks