SlipSlack
Aerospace
- Sep 15, 2004
- 1
I need to display schedule slip calculated in calendar days. My project calendar is set up in work days (5 day weeks, 8 hour days).
Is there a way to display slip in calendar days on the table portion of the GANTT view? I have used the "Schedule Varience" selection, but the calculation is apparently based on the 5-day work schedule associated with the project.
Is there a way to display slip in calendar days on the table portion of the GANTT view? I have used the "Schedule Varience" selection, but the calculation is apparently based on the 5-day work schedule associated with the project.