Jan 18, 2012 #1 qaengineer1969 Mechanical Joined Dec 1, 2010 Messages 8 Location GB Can anybody help me and tell me what schedule Carbon Steel Pipe I need to use on High Pressure Air Lines at 40 Bar
Can anybody help me and tell me what schedule Carbon Steel Pipe I need to use on High Pressure Air Lines at 40 Bar
Jan 18, 2012 #2 TGS4 Mechanical Joined Nov 8, 2004 Messages 3,983 Location CA Depends on the Code of Construction, diameter, grade of carbon steel, etc. Start with your Code of Construction. Follow that through. Upvote 0 Downvote
Depends on the Code of Construction, diameter, grade of carbon steel, etc. Start with your Code of Construction. Follow that through.
Jan 18, 2012 #3 Duwe6 Industrial Joined Jul 27, 2010 Messages 2,189 Location US Sch 40 will work, but I would use Sch 80 up to about 4"NPS. Then I would do an engineering eval using the code of construction. If no c-of-c is mandated, use ASME B31.3. It is excellent. Upvote 0 Downvote
Sch 40 will work, but I would use Sch 80 up to about 4"NPS. Then I would do an engineering eval using the code of construction. If no c-of-c is mandated, use ASME B31.3. It is excellent.