Hi Guys,
Hope soem one has tackled this issue recently.
I am just designing a 45 degree three girder system steel box girder deck rail bridge where the adjacent tracks are supported on two decks in between these three box girders which comprise of steel decking stiffened by t section below steel deck.
This is regarding camber to these steel boxes.
The bridge is skew but at every square cross section the soffit of the girders must be at the same level so as the achieve a horizontal deck section at any square xsection along the length of the bridge.
If some one has dealt with this kind of issue can you let me know how camber was applied to the girders?
Cheers
Hope soem one has tackled this issue recently.
I am just designing a 45 degree three girder system steel box girder deck rail bridge where the adjacent tracks are supported on two decks in between these three box girders which comprise of steel decking stiffened by t section below steel deck.
This is regarding camber to these steel boxes.
The bridge is skew but at every square cross section the soffit of the girders must be at the same level so as the achieve a horizontal deck section at any square xsection along the length of the bridge.
If some one has dealt with this kind of issue can you let me know how camber was applied to the girders?
Cheers